Welding and Connection of Pipework
The final connection and of the heat collectors to the pipework leading to the heat pump has been completed. All pipe work was electrofused
Solar Assisted Ground Source
The final connection and of the heat collectors to the pipework leading to the heat pump has been completed. All pipe work was electrofused
Today a Thermal Response Test (TRT) was completed on the GeoKoax Borehole at the Druids Glen site. The purpose of the Thermal Response Test is to determine the ground thermal …
The downhole sensor system described here was completed by the 21st October. The sensors were inserted downhole along with the collectors earlier in September, but successful installation of the thermocouples above ground …
The team returned to the Druids Glen Site on the 23rd of September to backfill the three successfully drilled holes with a special thermally conductive grout. The grout used was “ThermoCem …
Drilling on the Druids Glen site commenced on the 14th of September and ran until 16th of September. The drilling was conducted by Nicholas Wall of Walls Well drilling. Drilling …